The Urgent Need for FAA’s Air Traffic Control Modernization

The Federal Aviation Administration (FAA) is at a critical juncture in its efforts to modernize the nation’s air traffic control (ATC) systems, according to a recent report by the Government Accountability Office (GAO). The GAO-25-108162 report, presented by Heather Krause, Managing Director of Physical Infrastructure, highlights serious concerns about the sustainability of ATC infrastructure and the slow pace of modernization efforts. A 2023 outage that temporarily grounded flights across the country underscored the urgency of addressing aging ATC systems, yet progress has been sluggish and fragmented.

The report reveals that out of 138 ATC systems evaluated by the FAA, 51 were found to be outright unsustainable, while another 54 were potentially unsustainable. These systems play a crucial role in managing navigation, communication, surveillance, and air traffic operations, making their deteriorating condition a direct threat to flight safety and efficiency. FAA’s modernization initiative, known as the Next Generation Air Transportation System (NextGen), has faced significant delays, with key system improvements now projected to take six to ten years or longer. Despite its multi-billion-dollar budget, NextGen has struggled to meet milestones, with progress hindered by funding uncertainties, bureaucratic inefficiencies, and external disruptions such as the COVID-19 pandemic.

A key problem identified in the GAO report is FAA’s ineffective risk management and investment oversight. The agency lacks a systematic approach to prioritizing modernization projects, meaning that even the most critical and at-risk systems have not been fast-tracked for upgrades. FAA’s acquisition oversight processes also fall short, with many projects taking years to establish cost and performance baselines, leading to inefficiencies and prolonged delays. The report criticizes FAA’s failure to conduct regular life-cycle cost assessments for NextGen, a deficiency that has contributed to funding constraints and planning uncertainty.

Beyond financial and managerial hurdles, the complexity of modernizing ATC systems is further complicated by technological and operational challenges. The integration of new technologies, including digital communication systems and trajectory-based flight planning, depends on aircraft operators equipping their fleets with compatible systems, which has been inconsistent across the industry. Additionally, new entrants into U.S. airspace, such as drones and commercial space operations, are increasing the demand for a more adaptable and resilient ATC infrastructure. Cybersecurity risks and concerns over 5G interference with aircraft navigation systems add further complications to an already strained modernization effort.

The GAO has issued several recommendations aimed at improving FAA’s modernization strategy. Chief among them is the need for FAA to develop a comprehensive risk mitigation plan that prioritizes ATC system upgrades based on urgency and impact. The report also calls for increased transparency in how FAA reports modernization progress to Congress, particularly concerning funding and investment decisions. While FAA has agreed to some of these recommendations, many remain unaddressed, leaving critical ATC vulnerabilities unresolved.

With air travel demand expected to grow and operational complexities increasing, the FAA must act decisively to modernize ATC systems before another major outage disrupts national airspace. The stakes are too high for continued delays, and both Congress and industry stakeholders must push for greater accountability and efficiency in FAA’s modernization efforts. Until meaningful reforms are implemented, the risks posed by aging ATC infrastructure will continue to threaten the safety and reliability of U.S. air travel.

This blog post is based on GAO-25-108162 and does not guarantee accuracy or provide legal advice

Previous
Previous

The U.S. Coast Guard’s Infrastructure Crisis: $7 Billion in Unmet Needs and Growing Challenges

Next
Next

The Pentagon’s Real Estate Challenge: Underutilized Facilities and the Push for Accountability