When to use Bilateral vs. Unilateral Modifications in Federal Contracting

Contract modifications are a fundamental aspect of federal government contracting, allowing for adjustments to the terms, scope, or conditions of an agreement when circumstances change. The Federal Acquisition Regulation (FAR) governs the procedures for these modifications, which may be executed either bilaterally, requiring signatures from both the contractor and the government, or unilaterally, signed solely by the contracting officer. Understanding when to use each approach is crucial for contractors to ensure compliance, protect their interests, and maintain a productive working relationship with the government.

Bilateral modifications, also known as supplemental agreements, are used when the changes to the contract require the mutual consent of both parties. These modifications are essential when the adjustments impact the substantive rights or obligations of the contractor or the government. For example, when the government issues a change order under the Changes clause, adjustments to the contract’s price, schedule, or other terms often necessitate negotiation and agreement between the parties. Changes to the scope of work, such as adding new deliverables or removing specific requirements, also require bilateral modifications. In these cases, the contractor and the government must agree on the equitable adjustments to compensation, timelines, or other affected aspects of the contract.

Another scenario that calls for a bilateral modification is when a previously issued unilateral change order needs to be definitized. Often, the government issues unilateral modifications to address urgent needs or changes within the general scope of the contract. However, these changes may later require negotiation to finalize their impact on costs or schedules. For instance, if the government directs the contractor to implement additional safety measures during project execution, the contractor may incur unanticipated costs or delays. The parties must then agree on how these changes will affect the overall contract.

Bilateral modifications are also used in novation agreements, which occur when a contractor’s responsibilities under a contract are transferred to another entity. Such transfers often result from mergers or acquisitions, requiring both parties to agree on the new terms and document them accordingly. Similarly, disputes or claims that arise during contract performance often require bilateral modifications to reflect negotiated settlements. For example, if a contractor encounters unforeseen site conditions that increase costs or delay performance, the resolution of these claims will typically be documented in a bilateral modification.

Termination settlements also frequently involve bilateral modifications. When a contract is terminated for convenience, the government and the contractor must agree on terms for compensating the contractor for work performed, materials purchased, and any other costs incurred before termination. These negotiated settlements are formalized through bilateral modifications to ensure clarity and fairness for both parties.

On the other hand, unilateral modifications are executed solely by the government contracting officer and do not require the contractor’s consent. These modifications are often used when immediate action is necessary, or when the changes are administrative and do not affect the substantive terms of the contract. For example, administrative changes such as correcting a typographical error in the contract, updating a payment address, or revising accounting information can be implemented unilaterally without requiring the contractor’s signature.

Unilateral modifications are also commonly used to exercise contract options. Many government contracts include options for additional performance periods or quantities of deliverables. When the government decides to exercise these options, the action is typically documented through a unilateral modification, as the exercise of options is already contemplated in the original contract terms.

Another significant use of unilateral modifications is for change orders issued under the Changes clause. This clause allows the government to make unilateral adjustments within the general scope of the contract, such as altering work requirements or delivery schedules. In these situations, the government may direct the contractor to proceed with the changes while deferring negotiations on cost and schedule impacts. For example, if an agency requires an expedited delivery of goods due to an unforeseen operational need, the contracting officer may issue a unilateral modification to reflect the change in schedule. The contractor, however, retains the right to request an equitable adjustment to address any additional costs or delays resulting from the change.

Termination notices are another area where unilateral modifications are frequently applied. Contracts terminated for default or convenience often begin with a unilateral modification notifying the contractor of the termination. The terms of the termination, including any associated costs or penalties, may later be negotiated and formalized through a bilateral modification if necessary. Additionally, certain FAR clauses authorize the government to make unilateral changes, such as reducing the contract price due to defective pricing or enforcing liquidated damages for performance delays.

Incremental funding is another scenario in which unilateral modifications are used. For contracts that are incrementally funded, the government may unilaterally add funding up to the contract’s ceiling without requiring the contractor’s agreement. This approach ensures continuity of contract performance without delay.

For contractors, understanding the distinction between bilateral and unilateral modifications is critical. When dealing with bilateral modifications, contractors should be prepared to engage in negotiations to ensure that their interests are adequately protected. This includes clearly documenting any changes to costs, schedules, or other terms and ensuring that the modifications comply with applicable FAR requirements. Conversely, when faced with a unilateral modification, contractors must carefully review the modification to understand its implications and determine whether they need to submit a request for equitable adjustment or pursue other remedies under the contract.

The Changes clause is particularly important for contractors in this regard. When a unilateral change order is issued, the contractor has the right to request an equitable adjustment to address the impacts on cost, time, or other aspects of the contract. For example, if a unilateral change increases the complexity of the work or shortens the delivery schedule, the contractor may incur additional expenses or require additional resources. In such cases, the contractor should promptly submit a detailed proposal to the contracting officer to negotiate an appropriate adjustment.

Documentation is essential for both bilateral and unilateral modifications. Contractors should maintain thorough records of all modifications, including correspondence with the contracting officer, cost estimates, and any supporting documentation related to changes in scope or performance. Clear and comprehensive records can help contractors avoid disputes and ensure a smooth resolution if disagreements arise.

Ultimately, contract modifications are a powerful tool for addressing the evolving needs of federal contracts. Bilateral modifications enable mutual agreement on substantive changes, while unilateral modifications provide the government with flexibility for administrative or urgent actions. By understanding when and how each type of modification is used, contractors can navigate the process effectively, maintain compliance with FAR requirements, and protect their interests in the dynamic world of federal contracting.

This article its for informational purposes only and does not constitute legal advice. Contractors should consult with legal professionals for advice tailored to their individual circumstances.